Consider the following tasks, times, and predecessors for an assembly of set - top cable converter boxes: TASK ELEMENT TIME ( MINUTES ) PRECEDING TASKS

Consider the following tasks, times, and predecessors for an assembly of set-top cable converter boxes:
TASK ELEMENT TIME (MINUTES) PRECEDING TASKS
A 8
B 8 A
C 9 B
D 8 B
E 10 C, D
F 8 A
G 8 F
H 9 G
I 8 E, H
Given a cycle time of 25 minutes, develop two alternative layouts. Use the longest task time rule and the largest number of following tasks as a secondary criterion. What is the highest efficiency of your layout, assuming the 25-minute cycle time?
Note: Enter your answer as a percentage rounded to 2 decimal places.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Fundamentals

Authors: Robert N. Lussier

9th Edition

154438419X, 978-1544384191

More Books

Students also viewed these General Management questions