Consider the network presented in the following table. Calculate a . All possible paths b . The critical path c . The slack available at
Consider the network presented in the following table. Calculate
a All possible paths
b The critical path
c The slack available at any noncritical points
d The minimum project duration
tableImmediateTaskDuration DaysPredecessorsANoneBACADCEBD