Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Consider the project given below consisting of 1 2 different activities. Draw the network on node diagram of this project and use it to answer

Consider the project given below consisting of 12 different
activities. Draw the network on node diagram of this
project and use it to answer the four questions below.
1. which activities are directly dependent on activity A4?
2. which activities are directly or indirectly dependent on activity A4?
3. which activities are directly dependent on activity A5?
4. which activities are directly or indirectly dependent on activity A6?
5. what is the least tme that the projects takes to complete? please answer in "number of days". for instance, if the project takes 10 days to complete, please enter 10.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Information Systems

Authors: Jane Price Laudon, Ken Laudon

11th Edition

013607846X, 9780136078463

More Books

Students also viewed these General Management questions

Question

c 2/5 = 4, c =

Answered: 1 week ago

Question

=+c) Teachers ranking on their academic class of publications.

Answered: 1 week ago