Question
1 Approved Answer
Consider the project information in Table 1 , showing the WBS elements comprising the entire scope of a project, planned dates in baseline schedule, and
Consider the project information in Table
showing the WBS elements comprising the entire
scope of a project, planned dates in baseline
schedule, and actualplanned in updated schedules.
The projects planned duration was days.
Measurement of work element progress is by the
duration method.
i Draw the baseline schedule of the project as a
bar chart.
ii Draw the updated schedule for rd update as a
bar chart; Data Date DDd
Hint: you can combine bar charts for baseline
and updated schedules in one chart, if you
prefer
iii. Calculate the planned project progress by time from the baseline schedule.
iv Calculate the actual project progress on the DD of d
v Comment on the project time performance using:
a Project progress
b Project updated completion date
vi Analyze the reasons of delay
vii. Suggest suitable managerial actions to mitigate overcome the delays
WBS
Element
Baseline
Schedule
Schedule
Update
DD d
Start d Finish
d
Start
d
Finish
d
A A A
B A A
C A
D A A
E
A denotes an actual date, eg A means an
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started