Consider the project network shown below. Think about fast-tracking in the absence of resource constraints. Suppose activities 5-8 and 8-12 can be done in parallel.
Consider the project network shown below. Think about fast-tracking in the absence of resource constraints. Suppose activities 5-8 and 8-12 can be done in parallel. At what level of parallelization is the original critical path no longer the only critical path?