Question

1 Approved Answer

Consider the project performance report presented in figure 1 4 . 1 . What valid conclusion can you draw regarding the project cost performance as

Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project cost performance as of October 31,20XX?
WBS Element
Planned Value
(PV)
Earned Value
(EV)
Actual Cost
(AC)
2.01 Airframe
48000
48000
50000
2.02 Engines
22000
21000
23000
2.03 Avionics
80000
60000
45000
2.04 Communications
30000
30000
30000
2.05 Tech. Manuals
42000
42000
48000
2.06 Spares
40000
35000
42000
2.07 Training
80000
80000
86000
Project Total
342000
316000
324000
Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report
(October 31,20XX)
Question 19 options:
1)
The project is $8,000 over budget.
2)
The project is $18,000 over budget.
3)
The project is on budget.
4)
The project is $26,000 under budget.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Innovative Technology At The Interface Of Finance And Operations

Authors: Volodymyr Babich, John R. Birge, Gilles Hilary

1st Edition

3030757285, 978-3030757281

More Books

Students also viewed these General Management questions