Consider the project performance report presented in figure 14.1. Your analyst has determined that your estimate to complete (ETC) is $226,000. Based on your performance

Consider the project performance report presented in figure 14.1. Your analyst has determined that your estimate to complete (ETC) is $226,000. Based on your performance to date and assuming future performance will proceed at the same level of efficiency as past performance, what is your estimate at completion (EAC)?

image text in transcribed

WBS Element Planned Value (PV) 2.01 Airframe 48000 Earned Value (EV) 48000 Actual Cost (AC) 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions