Question
1 Approved Answer
Consider the project with 9 activities below: Suppose the following activities can each be extended by 1 day with the associated savings: Activity Saving ([)
Consider the project with 9 activities below: Suppose the following activities can each be extended by 1 day with the associated savings: Activity Saving ([) A 200 B 100 C 75 E 125 F 150 100 Which activities should be extended to maximize savings, without extending the overall project duration by more than one day? A B C