Consider the project with the following estimates for activity times and precedence relationships:
tableActivitytableOptimisticTimetableMostLikely TimetablePessimisticTimetableImmediatePredecessorsABCADBEBFC DGD EHF
a What is the expected duration of the project?
b What is the project variance?
c If the deadline of the project is days, what is the probability of finishing the project on time?