Consider the set of projects under consideration for Sox Corp. As the Manager of Finance for Sox Corp., you have been given a budget of
Consider the set of projects under consideration for Sox Corp. As the Manager of Finance for Sox Corp., you have been given a budget of $935,500 for capital projects. Which project will NOT be undertaken based on the numbers provided below by your analysts?
Project - Cost | NPV
A - 85,000 | 25,000
B - 270,000 | 37,500
C - 175,000 | 80,000
D - 275,000 | 125,000
E - 125,000 | 18,000
F - 275,500 | 72,000