Consider the simple 3 - station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i . e . , the

Consider the simple 3-station assembly line illustrated below, where the 2 machines at Station 1 are parallel, i.e., the product only needs to go through one of the 2 machines before proceeding to Station 2.
What is the bottleneck time of this process?
A.12min.
B.20min.
C.38min.
D.6min.
E.10min.
10. In the above question, what is the throughput time of this process?
A.12min.
B.20min.
C.38min.
D.18min.
E.58min.
11. Suppose that the demand in period 1 was 7 units and the demand in period 2 was 9 units. Assume that the forecast for period 1 was for 5 units. If the firm uses exponential smoothing with an alpha value of 20, what should be the forecast for period 3?(Round answers to two decimals.)
A.9.00
B.3.72
C.9.48
D.5.00
E.6.12
12. Service level is:
A. the probability of stocking out.
B. the probability of not stocking out.
C. something that should be minimized in retail.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management An Integrated Approach

Authors: R. Dan Reid, Nada R. Sanders

6th edition

1118952618, 978-1118952559, 1118952553, 978-1118952610

More Books

Students also viewed these General Management questions