construction accounting #59. The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. Actual costs at the

image text in transcribed

construction accounting

#59. The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. Actual costs at the end of the second week of the project indicate that in Fact Task A is $26,000, for B is $17,000 and for Task C is $16,500. CPI was previously calculated to be 0.97. Determine the total estimated cost at completion and cost to complete. Answer should be: Total Estimated cost at completion is $61,340 and Total Cost to complete is $1,840 SHOW ALL WORK PLEASE FOR A BETTER UNDERSTANDING WRITE NEATLY PLEASE

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managefirst Managerial Accounting With Pencil/Paper Exam

Authors: National Restaurant Association

1st Edition

0132283417, 978-0132283410

More Books

Students also viewed these Accounting questions

Question

Does it avoid use of underlining?

Answered: 1 week ago