construction accounting #59. The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. Actual costs at the
construction accounting
#59. The budgeted cost for Task A is $25,000, for B is $18,000 and for Task C is $16,000. Actual costs at the end of the second week of the project indicate that in Fact Task A is $26,000, for B is $17,000 and for Task C is $16,500. CPI was previously calculated to be 0.97. Determine the total estimated cost at completion and cost to complete. Answer should be: Total Estimated cost at completion is $61,340 and Total Cost to complete is $1,840 SHOW ALL WORK PLEASE FOR A BETTER UNDERSTANDING WRITE NEATLY PLEASEStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started