construction accounting The ACWP at the end of the second week for project C is $39,200 and BCWP= $38,100. What does this indicate? Answer should
construction accounting
The ACWP at the end of the second week for project C is $39,200 and BCWP= $38,100. What does this indicate? Answer should be: With a CPI of 0.97, the project is over budget SHOW ALL WORK PLEASE FOR A BETTER UNDERSTANDING WRITE NEATLY PLEASE