Question
Corp operates in the real estate industry. It employs a job-order costing system with labor hours as the cost driver. The company estimated overhead cost
Corp operates in the real estate industry. It employs a job-order costing system with labor hours as the cost driver. The company estimated overhead cost for the year would be Rp960,000 and labor hours would be 15,000. The following information is from the month of December of the current year:
House A House B House C House D
December construction activity:
Materials Rp80,000 Rp84,800 Rp57,200 Rp65,000
Direct labor cost Rp24,000 Rp36,000 Rp14,000 Rp21,000
Machine hours 400 700 900 800
Labor hours 1,200 1,800 800 1,500
Actual overhead cost incurred in December was Rp345,000. House B and House D were completed and sold for a total price of Rp650,000. House A was completed but not yet sold and House C was in process. Period costs totaled Rp42,000 and the income tax rate is 35%.
Required: Compute the amounts of the following items:
A. Cost of goods manufactured for December of the current year
____________________________
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started