15. Takt Time
1 point possiblo (graded)
75. A block making engine works 4 shifts daily for 6 days a week starting at 06.00.
Each shift is 5 hours long, but the first three shifts include a 35 minutes bresk
Customers' monthly demand is no000 blocks
Calculate the Takt Time in the period. (Assume 5 Weeks far a month)
9907 secs
90050340
397,03968
540.096006
450.55 secs
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management

Authors: Stephen P Robbins, Mary Coulter

11th Edition

9780273752776, 132163845, 273752774, 978-0132163842

More Books

Students also viewed these General Management questions

Question

1. Why are managers sensitive to media evaluations?

Answered: 1 week ago

Question

Term also regard to God......?

Answered: 1 week ago

Question

Poetic deals primarily with what genre......?

Answered: 1 week ago

Question

The work we call physics is more properly described what...?

Answered: 1 week ago

Question

Whose niece did Aristotle marry?

Answered: 1 week ago

Question

Which subject is Aristotle least known?

Answered: 1 week ago