Cost Account Planned Value Earned Value Actual Cost 1.2.1 $500 $250 $200 1.3.1 $150 $175 $175 Figure 1 32. Based on the data in Figure
Cost Account Planned Value Earned Value Actual Cost 1.2.1 $500 $250 $200 1.3.1 $150 $175 $175 Figure 1 32. Based on the data in Figure 1 above, Cost Account 1.2.1 is _____(of) schedule and _____ cost Group of answer choices Behind, over Ahead, on Ahead, over On, under Behind, under