Cost of capital components & WACC calculation: Weights After-tax Cost Weighted Cost After-tax cost of debt, r d (1 T) 15.00% Cost of preferred stock,

image text in transcribed

image text in transcribed

Cost of capital components & WACC calculation: Weights After-tax Cost Weighted Cost
After-tax cost of debt, rd(1 T) 15.00%
Cost of preferred stock, rp 10.00%
Cost of common stock, rs 75.00%
WACC =
Project acceptance analysis:
Projects Cost Expected Rate of Return Accept Project? Y/N
1 $2,000 16.00%
2 $3,000 15.00%
3 $5,000 13.75%
4 $2,000 12.50%
Formulas
Cost of capital components & WACC calculation: Weights After-tax Cost Weighted Cost
After-tax cost of debt, rd(1 T) 15.00% #N/A #N/A
Cost of preferred stock, rp 10.00% #N/A #N/A
Cost of common stock, rs 75.00% #N/A #N/A
WACC = #N/A
Project acceptance analysis:
Projects Cost Expected Rate of Return Accept Project? Y/N
1 $2,000 16.00% #N/A
2 $3,000 15.00% #N/A
3 $5,000 13.75% #N/A
4 $2,000 12.50% #N/A
Adamson Corporation is considering four average-risk projects with the following costs and rates of return: Expected Rate of Return Project 1 2 Cost $2,000 16.00% 3,000 15.00 5,000 13.75 4 2,000 12.50 The company estimates that it can issue debt at a rate of ra = 11%, and its tax rate is 40%. It can issue preferred stock that pays a constant dividend of $5 per year at $47 per share. Also, its common stock currently sells for $33 per share; the next expected dividend, D1, is $4.00; and the dividend is expected to grow at a constant rate of 5% per year. The target capital structure consists of 75% common stock, 15% debt, and 10% preferred stock. The data has been collected in the Microsoft Excel Online file below. Open the spreadsheet and perform the required analysis to answer the questions below. Open spreadsheet a. What is the cost of each of the capital components? Round your answers to two decimal places. Do not round your intermediate calculations. Cost of debt Cost of preferred stock % Cost of retained earnings b. What is Adamson's WACC? Round your answer to two decimal places. Do not round your intermediate calculations. c. Only projects with expected returns that exceed WACC will be accepted. Which projects should Adamson accept? Project 1 Project 2 Project 3 Project 4 WACC and optimal capital budget Nino Cost of debt, ra Tax rate, T Preferred dividend Preferred stock price, Pp Common stock price, Po Expected common dividend, D. Common stock constant growth rate, g. % common stock in capital structure % debt in capital structure % preferred stock in capital structure 11.00% 40.00% $5.00 $47.00 $33.00 $4.00 5.00% 75.00% 15.00% 10.00% 8 9 10 11 12 13

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Management In Construction Contracting

Authors: Andrew Ross, Peter Williams

1st Edition

1405125063, 9781405125062

More Books

Students also viewed these Finance questions

Question

Qin h FIG. 1 Dv LC Qout

Answered: 1 week ago