Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.80 per pound $ 8.40 Direct labor 5 hours at $7.20
Cost standards for one unit of product no. C77: | ||||
Direct material | 3 pounds at $2.80 per pound | $ | 8.40 | |
Direct labor | 5 hours at $7.20 per hour | 36.00 | ||
Actual results: | ||||
Units produced | 7,900 units | |||
Direct material purchased | 26,300 pounds at $3.00 | $ | 78,900 | |
Direct material used | 23,400 pounds at $3.00 | 70,200 | ||
Direct labor | 40,400 hours at $7.00 | 282,800 | ||
Assume that the company computes variances at the earliest point in time. The direct-material quantity variance is:
Multiple Choice
-
$840F.
-
$840U.
-
$7,280U.
-
$7,280F.
-
None of the answers is correct.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started