Could you please help me with question 2.1 and 2.2. thank you! You are the project manager assigned to a project. Use the information given
Could you please help me with question 2.1 and 2.2. thank you!
You are the project manager assigned to a project. Use the information given and complete the CPM calculations. 2.1 Develop a network diagram (5) 2.2 Use the table provided to formulate your answer. (15) Activity Duration in days 2 3 Preceding activity Start A A B C D F B D E F 1 5 3 3 Table to use for Question 2.2 ES EF LS LF Float Duration 2 3 Activity B D E F 1Step by Step Solution