course name system and project managment 5. A company has bagged a fixed cost contract for supply of 200 equipment or machines of same specifications at a cost of USD 60 million. The company estimated that the work can be completed in 20 days with 10 machines per day. The project status was reviewed after 16 days. It was noted at the time of review that only 120 machines have been installed and the cost incurred was USD 38 million. It was estimated at the time of review that a sum of USD 26 million would be required for completing the pending work that is installation of 80 machines. Make a performance analysis. 6. A manufacturing company needs to write an interim report for task 1 of project 1 during regular shift or on overtime. The project will require 500 man-hours at US\$20 per hour. The overhead burden is 75 percent on regular shift but only 5 percent on overtime. Overtime, however, is paid at a rate of time and a half. Assuming that the report can be written on either time, which is cost-effective - regular time or overtime? 5. A company has bagged a fixed cost contract for supply of 200 equipment or machines of same specifications at a cost of USD 60 million. The company estimated that the work can be completed in 20 days with 10 machines per day. The project status was reviewed after 16 days. It was noted at the time of review that only 120 machines have been installed and the cost incurred was USD 38 million. It was estimated at the time of review that a sum of USD 26 million would be required for completing the pending work that is installation of 80 machines. Make a performance analysis. 6. A manufacturing company needs to write an interim report for task 1 of project 1 during regular shift or on overtime. The project will require 500 man-hours at US\$20 per hour. The overhead burden is 75 percent on regular shift but only 5 percent on overtime. Overtime, however, is paid at a rate of time and a half. Assuming that the report can be written on either time, which is cost-effective - regular time or overtime