Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

course: project management PROJECT MANAGEMENT Crashing Example You are the project manager of the software installation project in the tables below. You would like to

course: project management image text in transcribed
image text in transcribed
image text in transcribed
PROJECT MANAGEMENT Crashing Example You are the project manager of the software installation project in the tables below. You would like to find the minimum cost-schedule for your project. Assume that partial crashing is allowed. What would be your minimum target completion time and total project cost? TIME ESTIMATES (WEEKS) FOR SOFTWARE INSTALLATION PROJECT Activity Immediate Predecessors Optimistic Most Likely Pessimistic s 13 A 8 10 12 D AB 2 4 B 3 D 10 EF 2 G 7 CF 9 7 A B 3 3 8 E F G H 1 1 6 1 $ 6 6 5 11 3 12 12 COST DATA FOR SOFTWARE INSTALLATION PROJECT Immediate Normal Cost Crash Time Crash Cost Activity Predecessors (S) (weeks) (5) 2.000 3 4,000 B 5.000 7 8,000 A 10.000 8 12.000 D AB 3,000 3 7,000 E B 4,000 2 5.000 F D 8,000 6 14,000 G EF 2.000 2 2.000 H G 6,000 5 9.000 1 CF 7.000 7 15.000 SOLUTION: TIME ESTIMATES (WEEKS) FOR SOFTWARE INSTALLATION PROJECT Activity Expected Time (62) (weeks) Variance, (0%) A 5 0.444 B 8 2.778 10 0.444 D 4 0.444 E 0.444 F 9.5 0.694 G 2 0.111 7.5 1.361 1 9 1.000 Project Network, Forward Pass, Backward Pass, and Slacks SC 7 01 215 3 12 12 215 O 1295215 Start 12 0 88 11 215235 31 0 8 10.5 185 235 0 235 3 215 22.5 235 7511 Crash Times and Costs Estimates Normal Time Activity (weeks) 5 B 8 C 10 D 4 E 3 F 9.5 G 2 H 7.5 1 9 Total Cost Normal Cost ($) 2,000.00 5.000.00 10,000.00 3,000.00 4,000.00 8,000.00 2.000.00 6,000.00 7.000.00 47.000.00 Crash Time weeks) 3 7 8 3 2 6 2 S 7 Crash Cost 5) 4,000.00 8.000.00 12.000.00 7,000.00 5.000.00 14,000.00 2.000.00 9,000.00 15.000.00 Maximum Crash Time 2 1 2 1 1 3.5 0 2.5 2 Crash Cost Per Week 1.000,00 3,000.00 1.000.00 4.000.00 1.000.00 1.714.29 NA 1,200.00 4,000.00 Initial Solution Project Duration Normal Cost Crash Cost (Cumulative) 31 weeks $47.000.00 0 Crashing Project Activities Initial Duration After Crashing n/a n/a Crashed Activity Crashed Time Paths ACI ADFI ADFGH BDFI BDFGH BEGH 24.0 27.5 28.0 30.5 31.0 20.5 Project Costs PROJECT MANAGEMENT Crashing Example You are the project manager of the software installation project in the tables below. You would like to find the minimum cost-schedule for your project. Assume that partial crashing is allowed. What would be your minimum target completion time and total project cost? TIME ESTIMATES (WEEKS) FOR SOFTWARE INSTALLATION PROJECT Activity Immediate Predecessors Optimistic Most Likely Pessimistic s 13 A 8 10 12 D AB 2 4 B 3 D 10 EF 2 G 7 CF 9 7 A B 3 3 8 E F G H 1 1 6 1 $ 6 6 5 11 3 12 12 COST DATA FOR SOFTWARE INSTALLATION PROJECT Immediate Normal Cost Crash Time Crash Cost Activity Predecessors (S) (weeks) (5) 2.000 3 4,000 B 5.000 7 8,000 A 10.000 8 12.000 D AB 3,000 3 7,000 E B 4,000 2 5.000 F D 8,000 6 14,000 G EF 2.000 2 2.000 H G 6,000 5 9.000 1 CF 7.000 7 15.000 SOLUTION: TIME ESTIMATES (WEEKS) FOR SOFTWARE INSTALLATION PROJECT Activity Expected Time (62) (weeks) Variance, (0%) A 5 0.444 B 8 2.778 10 0.444 D 4 0.444 E 0.444 F 9.5 0.694 G 2 0.111 7.5 1.361 1 9 1.000 Project Network, Forward Pass, Backward Pass, and Slacks SC 7 01 215 3 12 12 215 O 1295215 Start 12 0 88 11 215235 31 0 8 10.5 185 235 0 235 3 215 22.5 235 7511 Crash Times and Costs Estimates Normal Time Activity (weeks) 5 B 8 C 10 D 4 E 3 F 9.5 G 2 H 7.5 1 9 Total Cost Normal Cost ($) 2,000.00 5.000.00 10,000.00 3,000.00 4,000.00 8,000.00 2.000.00 6,000.00 7.000.00 47.000.00 Crash Time weeks) 3 7 8 3 2 6 2 S 7 Crash Cost 5) 4,000.00 8.000.00 12.000.00 7,000.00 5.000.00 14,000.00 2.000.00 9,000.00 15.000.00 Maximum Crash Time 2 1 2 1 1 3.5 0 2.5 2 Crash Cost Per Week 1.000,00 3,000.00 1.000.00 4.000.00 1.000.00 1.714.29 NA 1,200.00 4,000.00 Initial Solution Project Duration Normal Cost Crash Cost (Cumulative) 31 weeks $47.000.00 0 Crashing Project Activities Initial Duration After Crashing n/a n/a Crashed Activity Crashed Time Paths ACI ADFI ADFGH BDFI BDFGH BEGH 24.0 27.5 28.0 30.5 31.0 20.5 Project Costs

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Complete Idiots Guide To Personal Finance In Your 40s And 50s

Authors: Sarah Fisher, Susan Shelly

1st Edition

0028642732, 9780028642734

More Books

Students also viewed these Finance questions

Question

How to solve maths problems with examples

Answered: 1 week ago