CPM Select one: assumes we do not know ahead of time what activities must be completed. assumes that activity time estimates follow the normal probability
CPM
Select one:
assumes we do not know ahead of time what activities must be completed.
assumes that activity time estimates follow the normal probability distribution
is a deterministic network technique that allows for project crashing.
is a network technique that allows three time estimates for each activity in a project.