Crane Construction Company had a contract starting April 2021, to construct a $25100000 building that is expected to be completed in September 2023, at an

Crane Construction Company had a contract starting April 2021, to construct a $25100000 building that is expected to be completed in September 2023, at an estimated cost of $23100000. At the end of 2021, the costs to date were $13167000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $5900000 and the cash collected during 2021 was 3310000. Crane uses the percentage-of-completion method.
At December 31, 2021 Crane would report Construction in Process in the amount of:

$14307000.
$1140000.
$13167000.
$7267000.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions