Crane Corporation accumulates the following data relative to jobs started and finished during the month of June 2022. Costs and Production Data Actual Standard Raw

Crane Corporation accumulates the following data relative to jobs started and finished during the month of June 2022.

Costs and Production Data

Actual

Standard

Raw materials unit cost

$2.20 $2

Raw materials units

11,200 10,400

Direct labor payroll

$169,500 $161,120

Direct labor hours

15,000 15,200

Manufacturing overhead incurred

$214,452

Manufacturing overhead applied

$216,752

Machine hours expected to be used at normal capacity

41,500

Budgeted fixed overhead for June

$62,250

Variable overhead rate per machine hour

$3.10

Fixed overhead rate per machine hour

$1.50

Overhead is applied on the basis of standard machine hours. Three hours of machine time are required for each direct labor hour. The jobs were sold for $458,000. Selling and administrative expenses were $35,700. Assume that the amount of raw materials purchased equaled the amount used.

(a)

Compute all of the variances for (1) direct materials and (2) direct labor. (Round per unit values to 2 decimal places, e.g. 52.75 and final answers to 0 decimal places, e.g. 52.)

(1)

Total materials variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable

Materials price variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable

Materials quantity variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable

(2)

Total labor variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable

Labor price variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable

Labor quantity variance

$enter a dollar amount select an option FavorableUnfavorableNeither favorable nor unfavorable
(b)

Compute the total overhead variance.

(c) Prepare an income statement for management. (Ignore income taxes.)

*** PLEASE COMPLETE FULL PROBLEM

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_step_2

Step: 3

blur-text-image_step3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: John Hoggett, Lew Edwards, Evelyn Hogg, John Medlin, Matthew Tilling

8th Edition

ISBN: 1742466362, 978-1742466361

More Books

Students also viewed these Accounting questions