Crane has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2000 units, Crane used 3850 hours of labor
Crane has a standard of 2 hours of labor per unit, at $12 per hour. In producing 2000 units, Crane used 3850 hours of labor at a total cost of $46800. Crane's labor quantity variance is $600F.$1823F.$600U.$1800F