Answered step by step
Verified Expert Solution
Question
1 Approved Answer
CRASHING : EXAMPLE 2 Normal 0 A 4 4 c 5 5 F 10 A C Normal Direct Max Crash i 4 _' 4 4
CRASHING : EXAMPLE 2 Normal 0 A 4 4 c 5 5 F 10 A C Normal Direct Max Crash i 4 _' 4 4 ' 4 4 4 1 Act Time Pred Cost CrashTime Cost/Slope 4 4 8 8 1 9 H\\ 5 5 7 D 11 11 G 13 1 1 1 i 1 1 o B 7 8 4 12 12 2 14 D u o _ 4 U 7 7 7 0 7 E 12 12 H 14/ o o o B 5 i 12 12 2 14 1 \\ E H 5 5 4.2 If the indirect costs for each duration are $1,200 for 16 weeks, $1,130 for 15 weeks, $1,000 for 14 weeks, 5900 for 13 weeks, 5860 for 12 weeks, 5820 for 11 weeks and $790 for 10 weeks, compute the total costs for each duration. What is the optimum cost-time schedule? Project Activities Rem Activities Project Direct Resulting Indirect Total Project T= Crashed Crash Cost Costs Critical paths Costs Cost
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started