Crashing with POM Below are two printout tables from POM/DS software for crashing a project, with several questions that follow. Create a message and give

Crashing with POM

Below are two printout tables from POM/DS software for crashing aproject, with several questions that follow.

Create a message and give your answers to each question.

Provide justification for your answers bynoting how you used the tables to arrive at your answers.

Quiz Question Solution
Normal time Crash time Normal Cost Crash Cost Crash cost/pd Crash by Crashing cost
Project 12. 7.
A 7. 4. 500. 800. 100. 3. 300.
B 3. 2. 200. 350. 150. 1. 150.
C 6. 4. 500. 900. 200. 1. 200.
D 3. 1. 200. 500. 150. 2. 300.
E 2. 1. 300. 550. 250. 1. 250.
TOTALS 1,700. 1,200.

Created byDS for Windows

Quiz Question Solution
Project time Period cost Cumulative cost A B C D E
12 0. 0.
11 100. 100. 1.
10 250. 350. 1. 1.
9 250. 600. 2. 1. 1.
8 250. 850. 3. 2. 1.
7 350. 1,200. 3. 1. 1. 2. 1

The above two tablesreport findings from POM/DS software.

1) Assume you have alreadysuccessfullyreduced the project to 10 weeks. Now, decide whichactivity(ies) must additionally be crashed to reduce project time one more week (to go from 10 weeks to 9 weeks).

A and D,each for one week.

A, D, E; each for one week.

A, D, E:A for 2 weeks and B and E each for one week.

Can't be determined with the exhibits provided.

Other example question that one might ask about these computer outputs:

2) What is the total cost of this project under normal times?

3) How long will this project take under normal times?

4) Assumingample time and resources are allocated, how soon canwe complete this project? What would be the total cost of that completion time?

5) What would be the total cost to finish the project in 8 weeks?

6) To finish this project in 8 weeks, which activities must be crashed? What is the breakdown of the cost structure?

7) If you have taken steps to reduce project time to 9 weeks, but want to reduce it one more week so you can complete it in 8 weeks, which activities must be crashed to accomplish that one extra week of project time reduction?

8) Our contract promises project to be done in 12 weeks. But, for each week that we deliver it sooner, they pay a bonus of $300. Basedon cost and revenue data, inhow many weeks should we complete the project?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transportation A Global Supply Chain Perspective

Authors: John J. Coyle, Robert A. Novak, Brian Gibson, Edward J. Bard

8th edition

9781305445352, 1133592961, 130544535X, 978-1133592969

More Books

Students also viewed these Mathematics questions