Create a critical path method for the slab cycle activities with the restrictions that there is no overtime. Monday to Friday, 8 hours a day.
Create a critical path method for the slab cycle activities with the restrictions that there is no overtime. Monday to Friday, hours a day. Total project time length is working business days. The below activity and duration is in no particular order. Please ensure that it makes sense.
Activity Duration
Start typical slab cycle days
Buttonup and pour wall & column gang forms days
Clean and oil gang forms days
Cure columns & walls hours
Cure slab & landing hours
Hoist flyforms table forms for building slab days
Install duct work for kitchen & bath vents in slab days
Install electrical conduit in slab days
Install slab bottom reinforcing steel days
Install slab top reinforcement steel days
Install temporary handrails & shore slab below days
Install wall and column reinforcing & embedded conduit days
Install plumbing and electrical cans in slab days
Layout & install one side of wall and column gang forms days
Layout for slab inserts and embeds days
Level flyforms and construct infills for building slab days
Mount electrical boxes onto gang forms in columns & walls days
Place and finish slab, and stair landing day
Strip columns and walls gang forms days
End of typical slab days
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started