Create an MS Project with the following tasks and milestones. Task Name Predecessors Project started (milestone) Analyse Module A 1 Analyse Module B 1 Develop
Create an MS Project with the following tasks and milestones. Task Name Predecessors Project started (milestone) Analyse Module A 1 Analyse Module B 1 Develop Module A 2,3 Test Module A 4 Develop Module B 2,3 Test Module B 6 Integrate Module A 5,7 Integrate Module B 5,7 Project completed (milestone) 8,9 Improve the structure of this project by introducing summary tasks. Simplify the dependencies using milestones. Upload your MS Project file