Question
Create the following schedule using Microsoft Project (Set the start date as January 6, 2020) Activity Expected Duration Predecessors A 2 days B 3 days
Create the following schedule using Microsoft Project (Set the start date as January 6, 2020)
Activity | Expected Duration | Predecessors |
A | 2 days | |
B | 3 days | A |
C | 4 days | A |
D | 4 days | B, C |
E | 5 days | B |
F | 6 days | D |
G | 4 days | C, E, F |
and then answer the following questions:
1. Show the critical path (Task/Format/Check Critical Path box). Set current data as baseline schedule (Select Project/Set Baseline and accept defaults). Show comparison to baseline (Click Project/Format/Baseline and check Baseline box). What is the critical path, its duration, and expected finish date? Include a copy of the Gannt Chart
2. Assume that activities B and C are linked with a finish to finish relationship. Does that change the expected completion date for the project? How did the schedule change?
3. For activity F, add a lag of three days to its predecessor relationship with activity D. By adding the 3-day lag to F, what is the new expected duration for the project? How did the schedule change?
4. Suppose you now added a start to start relationship between activities F and G to the new Gantt chart. How does this additional relationship change the duration, expected completion date schedule?
5. Submit your project file and a copy of the final Gannet Chart.
Use the attached Template document file to present your answers.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started