Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Create the following schedule using Microsoft Project (Set the start date as January 6, 2020) and then answer the following questions: 1. Show the critical

image text in transcribedimage text in transcribed

Create the following schedule using Microsoft Project (Set the start date as January 6, 2020) and then answer the following questions: 1. Show the critical path (Task/Format/Check Critical Path box). Set current data as baseline schedule (Select Project/Set Baseline and accept defaults). Show comparison to baseline (Click Project/Format/Baseline and check Baseline box). What is the critical path, its duration, and expected finish date? Include a copy of the Gannt Chart 2. Assume that activities B and C are linked with a "finish to finish" relationship. Does that change the expected completion date for the project? How did the schedule change? 3. For activity F, add a lag of three days to its predecessor relationship with activity D. By adding the 3day lag to F, what is the new expected duration for the project? How did the schedule change? 4. Suppose you now added a start to start relationship between activities F and G to the new Gantt chart. How does this additional relationship change the duration, expected completion date schedule? 5. Submit your project file and a copy of the final Gannet Chart. Use the attached Template document file to present your answers

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ISE Project Management The Managerial Process

Authors: Erik W. Larson, Clifford F. Gray

8th Edition

1260570436, 978-1260570434

More Books