Crenshaw Enterprises has gathered projected cash flows for two projects. Year Project I Project J 0 $ 197,000 $ 197,000 1 95,500 72,600 2 87,600
Crenshaw Enterprises has gathered projected cash flows for two projects.
Year | Project I | Project J |
---|---|---|
0 | $ 197,000 | $ 197,000 |
1 | 95,500 | 72,600 |
2 | 87,600 | 77,800 |
3 | 65,200 | 81,400 |
4 | 59,800 | 87,000 |
At what interest rate would the company be indifferent between the two projects?
Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.
Which project is better if the required return is above this interest rate?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started