Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed that the cumulative planned value
Crista is a project manager for large project. She uses EVM on a regular basis. When calculating EVM Crista noticed
that the cumulative planned value is higher than cumulative earned value. What does this mean?
SPI is so project is doing well
SPI is so it is on schedule
SPI is ahead of time