Critical chain scheduling: Question 17Select one: a. is not concerned with resources. b. eliminates all buffers from the project. c. eliminates any buffers from individual
Critical chain scheduling: Question 17Select one: a. is not concerned with resources. b. eliminates all buffers from the project. c. eliminates any buffers from individual activities to create a project buffer. d. does not use feeding buffers. e. Uses feeding buffers, but not a project buffer