Question
1 Approved Answer
Critical Path is _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Critical Path is with a duration of days.
Draw the PERT diagram Given
Activity Predecessor Duration days
A
B A
C A
D B
E C
F D E
Use forward and backward pass to determine critical path and duration for the above project based on your PERT Diagram
ES Activity EF
LS Duration LF
Early Start Early Finish
Late Start Late Finish