Critical path method is a project network diagramming approach used to predict total project duration. Which of the following is not true of the critical
Critical path method is a project network diagramming approach used to predict total project duration. Which of the following is not true of the critical path?
a. | Critical path has the least amount of slack |
b. | Critical path determines the important activities in the project |
c. | Critical path is the longest path through the network diagram |
d. | Critical path is the earliest time by which the project can be completed |