Cumulative Average-Time Learning Curve Pohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design is subject to an 80 percent learning rate. Assume that the first unit produced takes 500 hours, and direct labor is paid an average of $40 per hour, Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one engine, two engines, four engines, eight engines, sixteen engines, and thirty-two engines, (Round hour answers to two decimal places.) Cumulative Number Cumulative Average Time per Cumulative Total Time: of Units Unit in Hours Labor Hours 1 2 4 8 16 32 2. What is the total tabor costi Pohlman manufactures the following number of engines; one, four, or sixteen? Cast for manufacturing one engine Cost for manufacturing four engines Cost for manufacturing sixteen engines What is the average cost per engine for the following number of engines: one, four, or sixteen? (Round your answers to the nearest dollar) Average cost per system for one engine 4 8 16 32 2. What is the total labor cost it Pohlman manufactures the following number of engines: one, four, or sateen? Cost for manufacturing one engine Cost for manufacturing four engines Cost for manufacturing sixteen engines What is the average cost per engine for the following number of enginest one, Four, or sixteen? (Round your answers to the nearest dollar) Average cost per system for one engine Average cost per system for fouif engines Average cost per system for sixteen engines 3. What If Pohlman is preparing a bid to build 16 engines? If necessary, round your answers to both parts to the nearest dollar Calculate budgeted labor cost for an engine design which Pohlman hos built before (assume that 16 of these engines had been made previously and the firse unit took 500 hours). Calculate budgeted labor cost for a new engine design that Pohlman's workers have never made before (assume the first unit will take 500 hours)