Curtiss Construction Company, Inc, entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,060,000. The building was completed on December 31, 2023 Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows Percentage of completion Costs incurred to date Estimated costs to complete wings to Axelrod, to date At 12-31-2021 At 12:31-2022 AT 12-01-2023 10% 60% 100% 5 368,000 $2,562,000 $4,321,000 3,240,000 1,708,000 721,000 2,190,000 4,064,000 Required: 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years Curtis concludes that the contract does not quality for revenue recognition over time 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2021 and 2022 as either cost in excess of bilings or billings in excess of costs Complete this question by entering your answers in the tabs below. Complete this question by entering your answers in the tabs below. Req 1 and 2 Reg 3 Assuming Curtis recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2021 and 2022 as either cost in excess of billings or billings in excess of costs. Balance Sheet (Partin) 2021 2022 Curront assets Current liabilities ( Req 1 and 2