d ) All of the above are true. 3 . Which of the following statements regarding PERT times is true? a . Optimistic time estimate

d) All of the above are true.
3. Which of the following statements regarding PERT times is true?
a. Optimistic time estimate is an estimate of the minimum time an activity will require.
b. Oplimistic time estimate is an estimate of the maximum time an activity will require.
C. The probable time estimate is calculated as t=(a+4m+b)6.
d. Pessimistic time estimate is an estimate of the minimum time an activity will require.
e. Most likely time estimate is an estimate of the maximum time an activity will require.
4. Which of the foltowing statements regarding critical paths is true?
a. The shortest of all paths through the network is the critical path.
b. Some activities on the critical path may have slack.
c. Every network has exactly one critical path.
(4) On a specific project, there can be multiple eritical paths, all with exactly the same duration.
e. The duration of the critical path is the average duration of all paths in the project network.
5. Which of the following statements regarding CPM is false?
a. The critical path is the shortest of all paths through the network.
b. The critical path is that set of activities that has positive slack.
c. Some networks have no critical path.
d. All activities on the critical path have their LS equal EF,
c. All of the above are false.
6. Which of the following statements concerning CPM activities is false?
a. The late finish of an activity is the earliest late start of all preceding activities.
b. The early finish of an activity is the early start of that activity plus its duration.
(c) The late finish is the earliest of the late start times of all successor activities.
d. The late start of an activity is its late finish less its duration.
e. The early start of an activity is the latest early finish of all preceding activities.
jA1
Which of the following statements regarding CPM networks is true?
T
Ais a
a. The early finish of an activity is the latest early start of all preceding activities.
b. The late finish of an activity is the earliest late start of all preceding activities.
(c.) On a specific project, there can be multiple critical paths, all of which will have exactly the same duration.
d. A project does not have to have a critical path:
e. All of the above are true.
Activities that are not on a PERT critical path but have little slack need to be monitored closely because
a. PERT treats ail activities as equally important
(6) near-critical paths could become critical paths with small delays in these activities
c. they are causing the entire project to be delayed
d. slack is undesirable and needs to be eliminated
c. they have a high risk of not being completed
Instructor: Dr. Abulghassem Masoud Alshaikh
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions