d ) All of the above are true. 3 . Which of the following statements regarding PERT times is true? a . Optimistic time estimate
d All of the above are true.
Which of the following statements regarding PERT times is true?
a Optimistic time estimate is an estimate of the minimum time an activity will require.
b Oplimistic time estimate is an estimate of the maximum time an activity will require.
C The probable time estimate is calculated as
d Pessimistic time estimate is an estimate of the minimum time an activity will require.
e Most likely time estimate is an estimate of the maximum time an activity will require.
Which of the foltowing statements regarding critical paths is true?
a The shortest of all paths through the network is the critical path.
b Some activities on the critical path may have slack.
c Every network has exactly one critical path.
On a specific project, there can be multiple eritical paths, all with exactly the same duration.
e The duration of the critical path is the average duration of all paths in the project network.
Which of the following statements regarding CPM is false?
a The critical path is the shortest of all paths through the network.
b The critical path is that set of activities that has positive slack.
c Some networks have no critical path.
d All activities on the critical path have their LS equal EF
c All of the above are false.
Which of the following statements concerning CPM activities is false?
a The late finish of an activity is the earliest late start of all preceding activities.
b The early finish of an activity is the early start of that activity plus its duration.
c The late finish is the earliest of the late start times of all successor activities.
d The late start of an activity is its late finish less its duration.
e The early start of an activity is the latest early finish of all preceding activities.
Which of the following statements regarding CPM networks is true?
Ais a
a The early finish of an activity is the latest early start of all preceding activities.
b The late finish of an activity is the earliest late start of all preceding activities.
c On a specific project, there can be multiple critical paths, all of which will have exactly the same duration.
d A project does not have to have a critical path:
e All of the above are true.
Activities that are not on a PERT critical path but have little slack need to be monitored closely because
a PERT treats ail activities as equally important
nearcritical paths could become critical paths with small delays in these activities
c they are causing the entire project to be delayed
d slack is undesirable and needs to be eliminated
c they have a high risk of not being completed
Instructor: Dr Abulghassem Masoud Alshaikh
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started