Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

D Fit TiF Time Time Cost Time Cost Activity Cost/ Day Normal Crash Normal Difference Difference A T $1000 B 3 2 $2,000 1 $10D

image text in transcribed
image text in transcribed
D Fit TiF Time Time Cost Time Cost Activity Cost/ Day Normal Crash Normal Difference Difference A T $1000 B 3 2 $2,000 1 $10D $100 6 1 $1000 5 $450 6 $1,000 2 E N 1 $1000 1 140 640 6 $1.000 4 $320 $1,000 2 $75 I. $1,OOD 1 560 $1.000 1 $150 $150 1. What is the project duration before compression? 21 days 18 days 19 days 23 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Marketing And Export Management

Authors: Gerald Albaum , Alexander Josiassen , Edwin Duerr

8th Edition

1292016922, 978-1292016924

Students also viewed these General Management questions