Question
1 Approved Answer
Daily Requirement: 3 8 , 6 8 0 units Number of shifts: one, 8 - hour shift, 4 0 hours per week. Downtime ( non
Daily Requirement: units Number of shifts: one, hour shift, hours per week. Downtime nonproductive, but paid minutes. Expected performance: Average workstation cycle time is
Provide the plant rate in units per minute to three decimal precision and do not include any type units, just the value to three decimal positions.