D'Arcy is managing a software development project. The Work Performance Report above, shows the project schedule and current performance information. D'Arcy believes that he
D'Arcy is managing a software development project. The Work Performance Report above, shows the project schedule and current performance information. D'Arcy believes that he will not be able to make the necessary adjustments for the project to finish on schedule, while the cost performance for the remainder of the project is likely to be as originally planned. What is the EAC(+-$10) for D'Arcy's project? D'Arcic Work Performance Data: End of Day Oct 3/11 Duratio Task Name System Installation System Analysis System Design System Developme System Testing System Deploymen Project Complete a) None of these b) $9,700 +- 100 c) $8,100 +- 100 d) $7,100 +- 100 e) $10,900 +- 100 n (days) 70 10 20 30 5 5 0 Start Aug 1/11 Aug 1/11 Aug 9/11 Aug 23/11 Oct 4/11 Oct 10/11 Oct 17/11 Finish Oct 17/11 Aug 12/11 Sept 5/11 Oct 3/11 Oct 10/11 Oct 17/11 Oct 17/11 Planned Actual Value Cost $9,000 $3,500 $500 $700 $1,000 $800 $6,000 $2,000 $1,000 $0 $500 $0 % Complete 48.9% 100.0% 90.0% 50.0% 0% 0%
Step by Step Solution
★★★★★
3.42 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
We need to calculated Earned Value of each task by following formula Earned Value Budgeted cost Comp...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3