Darius, marketing manager for Wankada Inc., was puzzled by the outcome of two recent bids to contract works. The company's policy was to bid 150%

Darius, marketing manager for Wankada Inc., was puzzled by the outcome of two recent bids to contract works. The company's policy was to bid 150% of the full manufacturing cost. One job (Job 100) had been turned down by a prospective customer, who had indicated that the proposed biding price of Wankada was $3 per unit higher than the winning bid. However, a second job (Job 101) had been accepted by a customer, who was agreeably amazed that Wankada could offer such favorable biding terms. This customer revealed that Wankada's price was $43 per unit lower than the next lowest bid.

Darius has been informed that the company was more than completive in terms of cost control.

Accordingly, he began to suspect that the problem was related to cost assignment procedures. Upon further investigating, Darius was told that the company uses a planwide (single) overhead rate based on direct labor hours. That rate is computed at the beginning of the year using budgeted data below.

Department A

Department B

Total

Overhead Costs

$500,000

$2000,000

$2500,000

Direct Labor Hours

200,000

50,000

250,000

Machine Hours

20,000

120,000

140,000

Darius was also told that the overhead costs in Department B were higher than those in Department A because Department B has more equipment, higher maintenance, higher power consumption, higher depreciation, and higher setup costs. In addition to the general procedures for assigning overhead costs, Darius was supplied with the following specific actual manufacturing data on Job 100 and Job 101:

Job 100

Department A

Department B

Total

Prime Costs

$100,000

$20,000

$120,000

Direct Labor Hours

5,000

1,000

6,000

Machine Hours

200

500

700

Units produced

14,400

14,400

14,400

Job 101

Department A

Department B

Total

Prime Costs

$10,000

$40,000

$50,000

Direct Labor Hours

400

600

1,000

Machine Hours

200

3,000

3,200

Units produced

1,500

1,500

1,500

Required Questions:

1- Using a plan wide (single) overhead rate based on direct labor hours, develop the bid prices for Job 100 and Job 101 (express the bid prices on a per unit basis).

2- Using departmental overhead rates (use direct labor hours for Department A and machine hours for Department B), develop per unit bid prices for Job 100 and Job 101.

3- Compute the difference in gross profit that would have been earned had Alpha used departmentalrates in its bids instead of the plan wide (in which case both jobs would have been accepted) rate.

Fully Explain Please!

4- Explain why the use of departmental rates in this case provides a more accurate.product cost.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Explain Coulomb's law with an example

Answered: 1 week ago

Question

What is operating system?

Answered: 1 week ago

Question

What is Ohm's law and also tell about Snell's law?

Answered: 1 week ago