Dasebre Ltd produces and sells one product with the brand name Sobolo. The standard cost for one unit being as follows: $ Direct material A
Dasebre Ltd produces and sells one product with the brand name Sobolo. The standard cost for one unit being as follows:
$
Direct material A - 10 kilograms at $20 per kg200
Direct material B - 5 litres at $6 per litre30
Direct wages - 5 hours at $6 per hour30
Variable production overhead50
Total standard cost310
The variable production Overheads is incurred in direct proportion to the direct labour hours worked. The budgeted sales volume for the month of May was 900 units at Standard price of $350
Actual results for the month of May are as follows:
Production and Sales800 units
Material A7,800 kg used, costing $ 159,900
Material B4,300 litres used, costing $ 23,650
Direct wages4,200 hours worked for $ 24,150
Variable production overhead$ 46,200
Sales proceeds$ 320,000
The Managing Director of Dasebre Ltd does not understand why there are differences between the standard and the actual costs and has tasked you as a Management consultant to undertake a variance analysis to investigate the differences recorded for the year under review.
Note: Computations are required to support your analysis
Required: Write your report to the Managing Director, highlighting all the possible variances in Material, Labour, Variable Overheads and Sales and their possible causes.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started