Question

1 Approved Answer

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity

Time (weeks)

Immediate Predecessor(s)

Activity

Time (weeks)

Immediate Predecessor(s)

A

7

E

5

B

B

7

F

5

B

C

3

A

G

11

C, E

D

3

A

H

7

D , F

Part 2

Dave's earliest start (ES) and earliest finish (EF) are:

Activity

ES

EF

A

enter your response here

7

Part 3

B

0

enter your response here

Part 4

C

enter your response here

10

Part 5

D

7

enter your response here

Part 6

E

enter your response here

12

Part 7

F

7

enter your response here

Part 8

G

enter your response here

23

Part 9

H

enter your response here

19

Part 10

Dave's latest start (LS) and latest finish (LF) are:

Activity

LS

LF

H

16

enter your response here

Part 11

G

12

enter your response here

Part 12

F

11

enter your response here

Part 13

E

7

enter your response here

Part 14

D

13

enter your response here

Part 15

C

9

enter your response here

Part 16

B

0

enter your response here

Part 17

A

2

enter your response here

Part 18

The slack times are:

Activity

Slack

A

enter your response here

Part 19

B

enter your response here

Part 20

C

enter your response here

Part 21

D

enter your response here

Part 22

E

enter your response here

Part 23

F

enter your response here

Part 24

G

enter your response here

Part 25

H

enter your response here

Part 26

The activities on the critical path are

A - D - H

B - F - H

A - C - G

B - E - G

.

Part 27

The total project completion time for Dave =

enter your response here

weeks.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The Restaurant From Concept to Operation

Authors: John R Walker

6th Edition

9781118139950, 470626437, 111813995X, 978-0470626436

More Books

Students also viewed these General Management questions

Question

What problems have I solved? What skills did that show?

Answered: 1 week ago