Question
David Ltd produces two products, A and B, in two production departments P1 and P2. The number of direct labour hours (DLH) and machine hours
David Ltd produces two products, A and B, in two production departments P1 and P2. The number of direct labour hours (DLH) and machine hours (MH) required to produce each product in each department is as follows:
Product AProduct B
Production departmentDLHMHDLHMH
P1 (Machining) 514 0.5
P2 (Assembly) 20.54 1
It is expected that 6000 units of product A and 2000 units of product B will be produced.
In addition to the two production departments, the company also has two service or support departments, maintenance (S1) and Quality Control (S2). For the coming year budgeted overhead is $300 000 made up as follows:
S1
Maintenance
S2
Quality control
P1
Machining
P2
Assembly
Total costs ($)
90 000
60 000
100 000
50 000
The consumption of support department services is as follows:
% Services Provided to: S1S2P1P2
% services
Provided by:
S1 0107020
S21006030
Required:
a)Calculate the plant-wide overhead rate assuming that direct labour hours is the cost driver.
b)Allocate the support department costs to the production departments using the direct method of allocation. Show all calculations.
c)Allocate the support department costs to the production departments using the step-down method of allocation. Show all calculations.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started