Dear Tutor, I need your help and the steps for the following question: Question 1 Draw an Activity Network Diagram for Project D based on
Dear Tutor,
I need your help and the steps for the following question:
Question 1
Draw an Activity Network Diagram for Project D based on the task table below:
Activity | Predecessor | Duration (Days) | Relationship |
A | - | 15 | - |
B | A | 4 | FS |
C | A | 7 | FS |
D | C, H | 20 | FS |
E | J | 13 | FS |
F | D, L | 14 | FS |
G | E, F | 5 | FS |
H | B | 8 | FS |
J | D | 9 | FS |
K A 8 FS
----------------------------------------------------------------------------------------------------------------------
L K 15 FS + 5
---------------------------------------------------------------------------------------------------------------------
Question 2
Identify the Critical Path(s) and the duration.
Question 3
What is the impact to the Critical Path if Task L was delayed by 10 days and Task G was completed early by 2 days? Explain your answer.
Thank you very much for your help.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started