Decomposition may not be possible for deliverable or subcontinent that will be accomplished far into the future the project management team usually wait until the
Decomposition may not be possible for deliverable or subcontinent that will be accomplished far into the future the project management team usually wait until the deliverable or subcontinent is agreed on so the details of WBS can be developed this technique is sometime referred to us rolling wave planning wateRfall planning creating WBS Iterative planning