Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM. An architect has been awarded a contract to prepare

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.

An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.

Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.

An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.

Job

Description

Predecessor

Expected time in days

A

Prepare preliminary sketches

NA

2

B

Outline specifications

NA

1

C

Prepare drawings

A

3

D

Write specifications

A B

2

E

Run prints

C D

1

F

Have specifications printed

B D

3

G

Assemble bid package

E F

1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial accounting

Authors: ramji balakrishnan, k. s i varamakrishnan, Geoffrey b. sprin

1st edition

471467855, 978-0471467854

Students also viewed these General Management questions