Define Critical path, Slack time, Resource Levelling and Dummy activity with reference to PERT and CPM. An architect has been awarded a contract to prepare
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Define "Critical path", "Slack time", "Resource Levelling" and "Dummy activity" with reference to PERT and CPM.
An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity.
Job | Description | Predecessor | Expected time in days |
A | Prepare preliminary sketches | NA | 2 |
B | Outline specifications | NA | 1 |
C | Prepare drawings | A | 3 |
D | Write specifications | A B | 2 |
E | Run prints | C D | 1 |
F | Have specifications printed | B D | 3 |
G | Assemble bid package | E F | 1 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started