Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Design-Bid-Build (DBB) The following is an example of a typical project. Evaluate the circumstances described and recommend how to proceed. Questions are offered for group

Design-Bid-Build (DBB)
The following is an example of a typical project. Evaluate the circumstances described and
recommend how to proceed. Questions are offered for group discussion. Be prepared to explain
and defend your recommendations.
A growing suburb of a large metropolitan city needed a new elementary school serving
grades K-5. It had a project budget of $7.5 million for site, construction, fees, and related costs.
State law required that the project be bid using Design-Bid-Build.
A local architect was hired and produced a design in a quick four months without any big
surprises. The project was advertised and bid for the statutorily required period. Eleven general
contractors purchased plans and began assembling their bids. For a variety of reasons, a
number of contractors dropped out of the competition. The architect, who was managing the
process, began to worry that not enough contractors were going to submit bids.
Bids were received at noon on the advertised date. A total of four bids were submitted for
general construction. The bids were opened, immediately checked for responsiveness, and then
read aloud. A clerk entered the bids onto a bid tabulation sheet. All bidders were determined to
be responsive. Highlights from the bidding were:
The four general construction bids ranged from $6,222,000 to $7,089,000, approximately a
10% spread.
The submitted bids were:
General Contractor #1 $6,222,000
General Contractor #2 $6,349,000
General Contractor #3 $6,978,000
General Contractor #4 $7,089,000
From the low bidder, five of eight submitted alternates were accepted:
Five alternates $472,500
Note: The total of these five alternates from the second lowest bidder was $363,300.
Related costs:
Property $485,500
Design fees $257,500
Total costs at signing of contracts $7,437,500
This amount was within the original budget, so the city awarded the contract to General
Contractor #1. Upon submission of a list of subcontractors, a time schedule, a schedule of
values, and other required submittals, contracts were signed. The contract completion date was
10 months after contract execution, and there were no liquidated damages. The job proceeded
slowly with a few issues:
The fire inspector required a change in the number of exit signs after contracts were
signed, causing an $11,520 change order.
An error on the topographic survey provided to the contractor during the bidding process
required an additional amount of fill material to be hauled in, resulting in a $30,780
change order.
The owner decided to upgrade wiring for technology in the classrooms, causing a
change order of $172,700.
The owner was forced to add additional electrical work. The design team had left out
electrical service to audio visual equipment that was being furnished by the owner and
installed by the contractor. This led to a $61,475 change order.
After the bids were turned in, the low millwork subcontractor withdrew its bid because it
found a significant mistake in its estimate. The general contractor decided to pay the
additional cost to go to the second bidder. No cost change was given.
Several minor changes, such as partition locations and door openings, were executed
without requests for extra payment.
The constructor requested a change order for special waterproofing that he claimed was
not covered by the contract documents. The owner rejected the request, saying that the
waterproofing was clearly implied by the documents, and ordered work to proceed,
including the flashing. The constructor sent a letter citing its position (request for extra
money) and continued work.
The owner agreed to pay the designer an additional $20,000 to incorporate all of the
changes on the drawings and to provide more onsite assistance. The school was
completed four weeks behind schedule, but the schedule did allow the school
employees to occupy the building during final construction so they could prepare the
school for the students. The punch list consisted of 250 items, which again caused
coordination problems.
The total project cost became:
At conclusion of bidding $7,437,500
Total of all change orders, extra costs + $516,561
= $7,954,061
At the dedication ceremony, the owner expressed satisfaction with the school building but
dismay that the project ended up over its original $7.5 million budget. He did not seem to feel
the reasons for this were entirely caused by the owner.
DISCUSSION ISSUES:
1. Do you think this project was typical of a Design-Bid-Build project? Why?
2. Why do you think some of the contractors dropped out during the bidding process?
3. What do the results of the four submitted bids indicate to you? Explain why you think it
was or was not a "good bid."
4. Does the difference in the amount between any of the bidders mean anything?
5. Besides being responsible for the design, the architect had other roles on this project.
What were they?
6. Was this a good application of the Design-Bid-Build delivery method? Is there additional
information you need to answer this question? If so, what would it be?
7. Did the Spearin Doctrine, highlighting the owner's responsibility for the architect's
performance, come into play on this project?
8. What is your reaction to the owner's thoughts at the end of the project?
9. What thoughts do you have about the low millwork contractor withdrawing its bid to the
general contractor after bidding? Should the owner have had to pay the extra costs to
use the next lowest bidder?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

People Centric Skills Interpersonal And Communication Skills For Financial Professionals

Authors: Danny M. Goldberg

2nd Edition

1119669308, 978-1119669302

More Books

Students also viewed these Accounting questions